Part 9 of 11
Roadmap and delivery
Thirty weeks from discovery to the full system, in four phases. Each phase ends with something working on the water, and the fleet is fitted only after the pilot proves the design.
Master schedule
Indicative timeline, confirmed after the site survey. Radio certification runs in parallel; using pre-certified modules shortens it.
What each phase delivers
Phase 1, weeks 1 to 8
MVP: see the fleet
- Tracker hardware with QZSS MADOCA-PPP positioning
- Live map with units, trails and zones
- Geofences for dock, riding, swim and restricted zones
- Staff alerts by push and WhatsApp
- Pilot on 1 to 3 jet skis
Done when pilot units report reliably for two weeks and geofence alerts reach staff within 30 seconds.
Phase 2, weeks 9 to 14
Rental lifecycle
- Check-out and check-in flows, rental board
- Rental timelines, route segments and stop durations
- Trip reports and daily operations reports
- Offline buffering verified end to end
- Fleet installation and staff training
Done when every rental for a full week runs through the app with no paper fallback.
Phase 3, weeks 15 to 22
AI layer
- Anomaly detection with explained alerts
- Towing and out-of-hours detection
- Predicted return times and late-return nudges
- Staff feedback loop for false alerts
Done when false alerts stay under 0.5 per unit per day and predicted returns land within 3 minutes for 80% of trips.
Phase 4, weeks 23 to 30
Sensor fusion and analytics
- Tamper detection: lid, power cut, antenna
- IMU fusion for capsize and towing confidence
- Engine hours and service reminders
- Heatmaps, utilisation and zone analytics
Done when tamper tests pass on every unit and the owner receives the first monthly operations report.
Validation and testing
Testing happens on the real beach with real jet skis, not just in the lab.
Field testing
Signal strength mapped across the whole operating area for each network, so dead spots are known before go-live. Reporting interval tested against data use and backup battery life.
Accuracy calibration
Tracks compared against surveyed ground-truth markers at the dock, corridor entrance and zone corners, with and without QZSS MADOCA-PPP. Geofence buffers sized from the measured drift.
Reliability testing
Power loss, submersion, hose spray, vibration on the trailer and at speed, antenna detachment and case opening, each with a written pass criterion.
Pilot deployment
One to three jet skis on normal rentals for at least two weeks, measuring the figures below every day.
Pilot measures
| Measure | Pilot target |
|---|---|
| Tracking uptime during operating hours | 98% or better |
| Fixes delivered, including backfilled | 99% or better |
| Missed critical events | None |
| False alerts | Fewer than 0.5 per unit per day |
| Event to staff alert | 30 seconds or less, 95% of alerts |
| Fixes with MADOCA-PPP converged during rentals | 90% or better |
| Check-out time | Under 60 seconds |
Engagement model
Three stages, each with its own decision point. Commercial terms are set out in a separate quotation once the site survey confirms fleet size, models and coverage.
Pilot
Site survey, 1 to 3 trackers installed, MVP platform and staff app, two weeks of measured operation and a pilot report with a go or no-go recommendation.
Fleet rollout
Trackers for the whole fleet, installation, Phases 2 to 4, staff training in English and Bahasa Melayu, and go-live support on the beach.
Managed service
Per-unit monthly subscription covering connectivity, hosting, updates, model tuning, monitoring and support, with an agreed response time for faults.
What we need from the operator
- A named project contact and access to the dock and fleet for the survey and installs
- Fleet list with jet ski models, and the current zone or licence maps
- Two or three staff champions for the pilot and their feedback
- Booking or point-of-sale system details if integration is wanted